PROJECT SCOPE: Removal of three roof systems, Installation of a GAF 3ply system hotmopped over tapered Insulation on a concrete deck; Replace a/c stands, raise electrical conduits and re-shape condensation lines and install all new UV rated insulation; Wrap the parapet walls up and over and finish with a metal parapet cap.
OPTAMISS’ ROLE: Reviewed contract for technical scope; Obtained mechanical estimates for consideration by the Client; Performed construction project management and construction observation, Held weekly construction meetings; Reviewed and approved A1A Pay applications;